Airport Tank Progress Photos

October 7, 2015

10-7-2015-Forming-Tank-Lid

Forming Tank Lid. The contractor has finished pouring all exterior walls and has completed the formwork to pour the tank roof/lid.

October 27, 2015

10-27-2015-Booster-Walls-&-Tank-3

Booster Walls & Tank 3. The contractor has finalized the tank and has finished installing the masonry block for the Booster Station.

October 29, 2015

10-29-2015-Well-Test-Pit

Well Test Pit. The contractor has is performing the test pumping for the replacement well. The water is discharging at 2,000 gallons per minute (gpm) to understand aquifer characteristics and recovery.