WPC Phase 1 Project Update

August 4, 2015

8

Excavation and dewatering for the UV Building

9

Demolition of the Chlorine Contact Basins

5

Contractor excavating for one of the split structures

1

Structural Modification in the aeration basins

6

Contractor installing base material where the UV Building will be constructed

10

PVC coated conduit has been installed around the aeration basins to provide power and communication to the future mixers.  This conduit is specifically designed to withstand the corrosive environment found in a wastewater treatment plant.  The mixers will be installed in the basins to promote efficient and effective treatment of the wastewater.